Hi
I have an existing mm plan in one of the server which contain
1.Check integrity
2.Shrink
3. Reorganize
4.Rebuild
5.Update stats
Does both Reorganize and Rebuild required in the same mm plan ? Only Rebuild will optimize the indexes ?
Currently re-org is taking 2 hrs to complete where Rebuils only 20 min .